Construction Continues to Move Forward at An Impressive Pace
There has been so much progress on-site since our last update, it is wonderful to see how fast things are moving. Each floor is rising quickly and it is truly exciting to see the building take shape week by week.
Here is a summary of the latest works over March and April:
Basement
– Shotcrete works to the basement are complete
– Blockwork completed
-Stud walls installed & flushing commenced
– Service runs 50%
Ground Floor
– Kingspan complete
– Blockwork commenced
– Service runs are approximately 50% completion
Level 1
– Firewalls installed
– Service runs are approximately 70% completion
– Window subframes installed
Level 2
– Window subsills set to commence next week
– Firewalls installation to follow window subsills
Level 4
– Concrete elements complete
– Formwork stripping commenced
Level 5
– Concrete elements are approximately 75% completion
Level 6
– Formwork deck are approximately 50% completion
– Concrete vertical elements are approximately 65% completion
We are currently anticipating the Level 7 suspended slab to be completed around the end of May, with internal fit out progressing on Levels 1- 3.
I hope you have enjoyed this update and I look forward to sharing the next one with you as the construction continues to progress.